Days 50 800-280-8862
At this point all the drywall is complete and the interior walls have received two coats of semi gloss white paint. All the interior doors have been hung and the front
door is installed. The white finish stucco, including the eaves and trim, is completed in 1 day. Some pictures reflect wet and dry appearance of the stucco. Next the
cabinet frames are installed, the garage door is in and the tile setter begins his preperation.
![]() ![]()
|
||||||||||||||